  • Select filter_black in the top right of the screen and choose the steps you want to mark as "completed" from the list. If you want to mark everything in the work package as completed, click the check mark button without filtering.

  • Click the check mark button at the top right of the screen, and click OK.

  • You can also use the check mark button to remove all progress for any package. If all of the worksteps in a particular view or list are completed, then pressing the button will undo all the progress for the work steps. This is equally applicable to the filtered view for any particular work step.

  • When the Smart Construction server is configured to set the automatic IWP Actual Dates with progress, the start and finish dates will reflect the date that the IWP was successfully synced to the server and will be in the time zone of the client initiating the action (and not the time zone of the Smart Construction server). This functionality is available with Smart Construction Version 8 HotFix 14 and later.