Upgrade a Smart Construction project with a custom PBS - Intergraph Smart Construction - 2019 (7.0) - Installation & Upgrade - Hexagon PPM

Intergraph Smart Construction Installation and Upgrade (2019)

Language
English
Product
Intergraph Smart Construction
Search by Category
Installation & Upgrade
Smart Construction Version
2019(7.0)

If you are upgrading to Smart Construction with a project that uses a custom PBS structure, complete the following steps:

  1. Delete previously created custom search criteria.

  2. Run the Smart Construction Custom PBS Utility tool to create new custom search criteria. For more information, see Configure a PBS with the Smart Construction PBS Configuration Utility.

    The Smart Construction Custom PBS Utility tool generates two XML files that must be loaded into Smart Construction - 02_SPC_PBS_AuthoringSchema.xml and 051-02-SPC_PBS_CustomSearchCriteriaData.xml.

  3. Load the 02_SPC_PBS_AuthoringSchema.xml file using the Import Schema Wizard. For more information, see Import Smart Construction schema.

  4. Load the 051-02-SPC_PBS_CustomSearchCriteriaData.xml file using the Loader.

    SHARED Tip You can load the 051-02-SPC_PBS_CustomSearchCriteriaData.xml file when you load the administrative files for Smart Construction. For more information, see Load the Smart Construction administrative files after the upgrade.

  5. Continue upgrading your system by running the Smart Construction Administrative Files. For more information, see Load the Smart Construction administrative files after the upgrade.

For more information, see Configuring a Custom Plant Breakdown Structure (PBS) for Smart Construction.