  • Rotate the mouse wheel in the calendar heading of the timeline to zoom in and out of the timeline.

  • Completion is indicated with a horizontal line on the IWP in the timeline. Hover over the IWP in the timeline to view details.

  • Click the Actual/Planned toggle key to change between Planned and Actual dates on the Work Package Schedule window. Planned dates display in blue, and Actual dates display in green. When you select Planned, the Work Package Schedule window displays Planned dates for each IWP. If no planned dates are set, the window displays any Actual dates that are set. When you select Actual, the Work Package Schedule window displays Actual dates for each IWP. If no actual dates are set, the window displays any Planned dates that are set. If Planned and Actual dates are not set, the Work Package Schedule window displays start date as today's date and finish date as next day's date.

  • Select one or more IWPs in the Work Package Schedule window and drag them to reorder the sequence of IWPs in the window and timeline. The white divider line displays where the IWPs move in the IWPs list.

  • Non-working days are indicated with hash marks .

  • The current date is indicated with a vertical line.

See Also