Remove the relationship between IWPs on the Work Package Schedule window - Intergraph Smart Construction - 2019 (7.0) - Help - Hexagon PPM

Intergraph Smart Construction Help (2019)

Language
English
Product
Intergraph Smart Construction
Search by Category
Help
Smart Construction Version
2019(7.0)
SmartPlant Foundation / SDx Version
10
  1. Click Work Package Schedule on the project home page to open the Work Package Schedule window.

  2. Select the relationship you want to remove in the Work Package Schedule timeline.

  3. Right-click the relationship line and select Delete to remove the relationship.

To remove relationships between multiple IWPs of the same type, press CTRL or Shift and select multiple IWPs in the Work Package Schedule window. Click Actions > Delete dependencies then select the type of dependency to delete. The dependencies for that type of relationship are deleted.

See Also

View, navigate, and manage the Work Package Schedule