Create an IWP based on another IWP - Intergraph Smart Construction - 2019 (7.0) - Help - Hexagon PPM

Intergraph Smart Construction Help (2019)

Language
English
Product
Intergraph Smart Construction
Search by Category
Help
Smart Construction Version
2019(7.0)
SmartPlant Foundation / SDx Version
10

You can create an IWP based on another IWP by copying it.

  1. Open an IWP.

  2. Click Copy on the Overview tab.

  3. Fill out details for the IWP.

  4. Click Next, and then select the information you want to copy to the new IWP from the Options tab or a custom tab.

Tab

What is added to the new IWP

Package Details

Copies the scope and notes, files, and snapshots from the original IWP to the new IWP.

Scope/Notes

The scope and notes from the original IWP are copied to the new IWP.

Files

All files are copied to the new IWP, along with the preference of whether the file is included in reports.

If files are configured to automatically attach to IWPs, the files are automatically added to the new IWP, based on how the files were configured.

Snapshots

All snapshots in the original IWP are added to the new IWP, along with any markups available on the snapshot.

Planning Data

Copies the construction responsibility and assigned user, components, drawings, and constraints from the original IWP to the new one.

Assignments

The construction responsibility and assigned user are copied from the original IWP to the new IWP.

Components

All components and drawings in the original IWP are added to the new IWP. Smart Construction validates the addition of components. For more information, see Resolve issues found while adding components.

Only unplanned engineered work steps are added to the new IWP. Manually added work steps and SIDs are not added to the new IWP.

Drawings

All drawings in the original IWP are added to the new IWP.

Constraints

All constraints in the original IWP are added to the new IWP. If the original constraint was marked as Met in the original IWP, it is added to the new IWP with the Met check box cleared.

Constraints that have hidden resources are not added to the new IWP.

For information on how to configure the Copy option on IWPs, see Update Smart Construction interface items.

See Also

Create and manage work packages