A constraint request can be submitted when you initially create a constraint, if you know everything that needs to be included in the request.

In most cases, you'll probably be returning to a saved preliminary request to fill in the required information, and then submitting it.

  1. Click a constraint to open the Constraint Request Form.

  2. In the Constraint Request Form, enter the information required to complete the request, such as the required date.

  3. Click Save.

    If a constraint request is submitted without the submitted date being specified, the current date will be used.

If you would like to create an automated workflow that would route the request to another user in the system, such as a resource manager, for completion or further processing, you can configure these changes in SmartPlant Foundation. For more information, see Configure the constraint management workflow.