This example details how to add a report selection criterion for CWP to the Contractor Progress by CWP report. After configuring the CWP report selection criterion, users must select a CWP before printing the Contractor Progress by CWP report.
-
Log on to SmartPlant Foundation Desktop Client as an administrator.
-
Find the Contractor Progress by CWP report.
-
Click Smart Construction > Find > Administration > Custom Reports.
-
Type Contractor Progress by CWP report in the Find Custom Reports dialog box.
-
Click OK.
-
-
Right-click the report name and select Manage Selection Criteria to open the Manage Selection Criteria dialog box.
-
Click Create a new item and relate it on the Manage Selection Criteria dialog box to open the SPC_ReportParam window.
-
Fill in criterion details on the SPC_ReportParam window. For this example, the report selection criterion is required for the user to select, and there is not a default value for the criterion.
-
Click Finish to save changes.
-
Click OK to add the report criterion to the custom report object.
-
Log on to Smart Construction.
-
Click Reports on the Home Page.
-
Select the Contractor Progress by CWP report.
-
On the Report Options dialog box, select a CWP number.
-
Click Print to print the report.