About project control tasks
A Project Control Task (PCT) is an equivalent record that maps to a master schedule activity.
The PCT module is designed to align activities related to construction, completions and commissioning defined in a master schedule so that the Smart Completions assignment functionality will associate relevant Planned Tasks. This allows you to link the level 6 planned tasks, managed in Smart Completions, to level 4 activities, managed in master scheduling systems such as Primavera P6, Ecosys, or Microsoft Project.
We recommend that only completions-related activities are loaded into Smart Completions. Otherwise, these activities will have no assigned planned tasks, and will not be updated with progressing.
API endpoints
-
ProjectControlTaskss - Create or update project control tasks, including assigning project control tasks to WBS phases, stages, and activities.
-
ProjectControlTasksAssets - Assign or remove an asset from a project control task.
-
ProjectControlTasksDocuments - Assign or remove a document from a project control task.
-
ProjectControlTasksPredecessors - Assign or remove a predecessor from a project control task.
-
ProjectControlTasksDetails - Access information about project control tasks for an instance or project.