The process for Creating a Notice of Energizations (NOE) is outlined below:

  1. To create a new NOE, select New.

    Notice of Energization Edit Form General Tab

  2. Complete Step 1 – General tab with the appropriate information. Choose the latest certificate available in CCMS. A valid C2 must be available to raise an NOE.

    Notice of Energization Edit Form What Needs to be Energized Tab

  3. Select Step 2 – What Needs to be Energized Tab and then select the appropriate assets.

    Notice of Energization Edit Form Documents Tab

  4. Click on Step 3 – Documents and select the appropriate documents.

    Notice of Energization Edit Form Required Approvers Tab

  5. Click on Step 4 and choose the Required Approvers.

    You can map the multi-sign-off of the approvers available in the user applications to the required approvers of NOE. When there is no sequence assigned, the default sequence of approvers is applicable.

    Notice of Energization Edit Form Comments Tab

  6. Click on Step 5 and add any comments if required, then click Save and close. CCMS will automatically assign your NOE with a unique NOE ID.

    Locate Notice of Energization

  7. Locate and select the NOE that was just created.

    Energization Limit Drawing

  8. To attach the marked up drawing(s), select the Energisation Limit Drawing button.

    Select and upload the drawing(s).

    Save and close edit form.

  9. The drawing(s) is now available for reference in the 'Scanned' column of the Primary Panel.