  1. In Project Management, click Integration > SDx Synchronization Status Monitor Command to open the SDx Synchronization Status window.

  2. Select a model in the Details Grid.

  3. Click Re-synchronize in the Synchronize to SDx Status panel to open the Re-synchronize dialog.

  4. If needed, select All Objects. By default, the Data Grid display is limited to data error objects.

  5. Select the design objects that need to be marked for synchronization to SDx.

  6. Click Re-synchronize to process the selected objects.

  7. Click Yes in the message box.

    When processing completes, the software displays a message that the selected objects have been marked and will be synchronized to SDx by the Share Service.

  8. Click OK to close the message box.

  9. Click Close to close the Re-synchronize dialog.

If you have the necessary level of access, you can also mark objects to be re-synchronized using the SDx Synchronization Status Monitor. Click Start > Intergraph Smart 3D > SDx Synchronization Status Monitor to display the SDx Synchronization Status Options. Follow the remaining steps listed above to mark the design objects.