  1. In the Project Management table (for As-Built), select the required project.

  2. Do one of the following:

    • On the Project Management table toolbar, click PPM All Outputs Graphic.

    • Right-click in the Project Management table and then click Find Completed Items to see which items have been completed in the project.

  3. Right-click in the Project Management table and then click Test Merge.