The following scenarios provide workflows for using projects in various configurations. You must perform the activities below before executing the workflows.

  1. In Smart Engineering Manager, do the following:

    1. Create a site.

    2. Create a plant.

    3. Associate the application.

    4. Create plant groups that allow drawings.

  2. In Smart P&ID Drawing Manager, create new drawings A - E and G, as shown.

  3. In , do the following:

    1. Open Drawing A.

    2. Create the following Assembly A-1 and assign the item tags as shown.

      PPM All Outputs Graphic

      • Choose vessel type Equipment > Vessels > Vertical Drums > Short 1D 1C 1to1.

      • Place both OPC partners in the Plant Stockpile.

    3. Open Drawings B, C, D, and G and place Assembly A-1 in each of the drawings.

      The software assigns unique item tags to the vessel, pipe runs, and OPCs in each drawing.

    4. Open Drawing E and place the instrument OPC partner from Drawing D.

  4. In Smart P&ID Drawing Manager, create a version of Drawing G and make a note of the version number (1).

  5. In Smart Engineering Manager, do the following:

    1. Enable projects for the plant.

    2. Create three projects: Project 1, Project 2, and Project 3 and for each, set the Project Scope at the level of the unit in which you created the drawings.

    3. Define Roles for each of the projects if not defined already.

  6. In Smart P&ID Options Manager, set the Claim Mode option to Shared.