It is possible to correct previously mapped costs in the case where mapping rules need to be changed. In this situation, it is necessary to re-map any costs that have already been pushed to the EcoSys cost control structure.

This can be accomplished by either updating the target of the mapping rule or completely resetting the mapped data for the project.