Click Schedule Management > Scheduling .
-
On the top of the Scheduling panel, click Preferences > General.
You can also set this preference in Production Planning and Smart Visualization.
-
You can do the following:
If you choose this
This happens
Baseline dates
Expected progress and delay durations of WBS items are calculated based on baseline dates. Any WBS item without baseline dates will not be included in the progress or delay duration calculation.
In Smart Visualization animations, the model elements are color coded based on baseline dates. Any model element associated to a work package without baseline dates will be either shown as future (purple color) or disables the animations based the selected visualization.
Current dates
Smart Visualization animations, expected progress and delay duration calculations are performed based on start and end dates.
-
Click Apply.