Calibration due report - HxGN EAM - 12.0.1 - Help - Hexagon

HxGN EAM Help

Language
English
Product
HxGN EAM
Search by Category
Help
HxGN EAM Version
12.0.1

Menu Path

Work > Reports > Calibrations > Calibration Due Report

Description

Displays a list of all open calibration work orders containing test points for which the planned completion date is less than or equal to the Due By date.

The planned completion date of a work order is calculated using the following formula:

Planned completion date = (Target date + Duration) - 1

If you select to include backlogged work orders, the number of days late for each work order are displayed in the report output. The number of days late is calculated using the following formula:

Days late = System date - Planned completion date

The System field in the report output displays all of the systems above the selected System/Equipment in an equipment hierarchy. If the selected System/Equipment has more than one parent in a hierarchy, each parent is displayed and each code separated with a forward slash (/), e.g., SYS1/SYS2/SYS3.

Related topics

Calibration due

Generating reports