Adding RCM failure mitigation for equipment - HxGN EAM - 12.0.1 - Help - Hexagon

HxGN EAM Help

Language
English
Product
HxGN EAM
Search by Category
Help
HxGN EAM Version
12.0.1

Add mitigation actions for failure modes defined on the RCM tab of the equipment screens. Failure modes can be mitigated by a PM schedule, by condition monitoring, by modifications, or by all these methods.

  1. Select one of these options:

    • Equipment > Assets

    • Equipment > Positions

    • Equipment > Systems

    • Equipment > Locations

  2. Select the equipment for which to define mitigation actions, and then click the RCM Failure Mitigation tab.

  3. Specify this information:

    Organization - Specify the organization associated with the mitigation.

    Failure Mode - Specify the failure mode for the mitigation.

    Mitigation Type - Specify the type of mitigation.

    Mitigated Probability - Specify the probability of the risk after being mitigated. The system will recalculate the Risk Priority Number (RPN) and populate the new Risk Level.

    Mitigation Applied - Select this check box to indicate that the mitigation is applied and included in the Risk Priority Number calculation of the equipment. The system will update the matching failure mode on the RCM tab for equipment, and may also update the Risk Priority Number (RPN) and the Risk Level on the equipment.

    Note - Optionally, specify a note for this mitigation.

    PM Schedule - Optionally, specify the PM Schedule to associate with the mitigation.

    Perform Every - Specify the frequency for the selected PM Schedule.

    You can also add a Maintenance Pattern or a PM Plan as part of the mitigation. You can also add a project or a case, for example if a modification is required, and an Aspect if condition based monitoring (inspections) may be required. These fields are optional and hidden on this tab.

  4. Click Submit.

  5. Click Activate Mitigation to activate the mitigation for the equipment. If clicked, the system will:

    • Add the equipment to the selected PM schedule if not already there and synchronizes the PM interval data.

    • Add the equipment to the selected Maintenance Pattern and activate it for the first sequence.

    • Add the equipment to the selected PM Plan.