Import an existing work order into an open MS Project scheduling session from HxGN EAM.

  1. Open MS Project.

  2. Select HxGN > HxGN EAM.

  3. Set the connection information for the HxGN EAM MS Project Interface.

  4. Click Import Existing Work Order.

  5. Specify this information:

    Work Order - Select the work order to import into MS Project.

    Work Orders must have at least one activity to be imported.

    An open scheduling session must exist to import existing work orders. If no open scheduling session exists for the project file, create or import a scheduling session prior to importing existing work orders.

  6. Click Import.