You can modify the relationships and constraints by creating a spreadsheet with Task Relation subject area and cost object relation subject areas. Once you configure the data, the changes are reflected in the scheduled Chart

  1. Navigate to Configure > Spreadsheet.

  2. In the General tab, enter the ID, Name, and select the Type as Task Scheduler Relation.

  3. Click Save.

  4. Click the Columns tab and then click Add New Column

  5. Expand Attributes, select the required task relation parameters

    • Source Task (Internal path ID)

    • Source Cost Object (Hierarchy path ID)

    • Relation

    • Lag

  6. Click ADD

  7. Click Save and Preview

    The chart is automatically refreshed. Similarly, you can create a spreadsheet with Cost object Relations subject areas.