You can modify the relationships and constraints by creating a spreadsheet with Task Relation subject area and cost object relation subject areas. Once you configure the data, the changes are reflected in the scheduled Chart
-
Navigate to Configure > Spreadsheet.
-
In the General tab, enter the ID, Name, and select the Type as Task Scheduler Relation.
-
Click Save.
-
Click the Columns tab and then click Add New Column
-
Expand Attributes, select the required task relation parameters
-
Source Task (Internal path ID)
-
Source Cost Object (Hierarchy path ID)
-
Relation
-
Lag
-
-
Click ADD
-
Click Save and Preview
The chart is automatically refreshed. Similarly, you can create a spreadsheet with Cost object Relations subject areas.