You must configure the following settings in the progress form
-
Create a form with a cost object or Task subject area.
-
In the Parameters tab, click the + sign and click Add New Column and select the following parameters
-
Cost Object Hierarchy Path or Task Hierarchy Path
-
ScheduleUIDatadate
-
-
Click the ScheduleUIDatadate parameter, under Type select the option Manual Entry and select the option for Display time component.
-
In the Edit Settings tab, for the Datadate field, do the following
-
Check the Readonly option under Settings to hide the Data date field from the chart
-
Under Save values, set the default save value to SchedulerUIDataDate
Externally scheduled columns cannot be progressed, set a Conditional Formatting rule to make Externally Schedule rows Readonly.
-