Generate Earned Value - EcoSys - 4.02 - Help - Hexagon PPM

EcoSys Projects Help (4.02)

Language
English
Product
EcoSys
Subproduct
Project
Search by Category
Help
EcoSys Standard Version
4.02

The Generate Earned Value action should be run after progress methods are established and progress method-specific attributes are updated. This procedure allows you to calculate % Complete, Earned Cost, Earned Hours, CPI, SPI, TCPI, TSPI, IEAC1, IEAC2, IEAC3, and EAC4 for the project and project period selected.

  1. Navigate to Progress > Earned Value.

  2. Click the Actions list and select Generate Earned Value.

  3. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    The Project displayed in the tool bar at the top of the screen is the only project available for selection in the Generate Earned Value dialog.

  4. Click the Project Period ellipsis to select the required period. By default, the last selected period appears.

  5. (Optional) Type the Comment.

  6. Click RUN and then OK.