This process will transfer the Project Schedule Resource Assignment requests for the selected Project to Staging Utilization for review and approval by the Resource Manager.

  1. Click the Actions list and select Push Resource Assignments to Resource Request Portal.

  2. Click the Project ellipsis and select the project from which you want to transfer resources to Staging Utilization.

  3. Click RUN and then OK.

    Only the resource assignments that have Hours will be pushed for approval.