This procedure allows you to map the schedule WBS to project CBS.

  1. Click the MAP TO PROJECT STRUCTURE tab and then click the SCHEDULE STRUCTURE tab.

  2. In the Map Schedule Structure to Project Structure Element panel, click the Link hyperlink against the WBS item which you want to map to the project structure.

  3. In the Project Structure Map Link panel, select the Link hyperlink against the project line item to which you want to map the WBS item.

    The WBS row in the Map Schedule Structure to Project Structure Element panel changes to green color and the Count of Mapping Rules value increases.

    Also, a transaction is created in the Mapping Rules panel with a unique Mapping ID.

    You can map multiple project line items with the same WBS item and vice versa.

  4. (Optional) Click the Object Name hyperlink to view the transactions related to the selected cost object in the Mapping Rules panel.

  5. Click SAVE.

  6. In the Mapping Rules panel, type the Mapping Sequence to set the sequence of the WBS item.

    If Mapping Sequence is left blank, Create Date will be used to factor sequence of mapping.

  7. Click the below ellipsis and select the required values:

    • Source Path ID - If required, change the Source Path ID

    • (Optional) Activity - Select the activity for this transaction

    • (Optional) Cost Account ID - Select the appropriate cost account

    • (Optional) Resource ID - Select the resource you want to assign to this transaction

      You can add or delete new and existing rows in Mapping Rules panel using Insert Row and Delete Row(s) icons.

  8. (Optional) Click the Update Target hyperlink and select the Target Cost Object to which you want to map the WBS item.

    The Target Object Path ID gets updated.

  9. Click SAVE. The fields Mapping ID and Create Date are auto-populated.

    Scheduling - Project Schedules - Schedule WBS Module - Activity Schedule tab - Spreadsheet tab - Schedule WBS Mapping tab_4.01