This procedure allows you to view the Bill Of Quantities (BOQ) item summary of the selected project object.

  1. Navigate to Estimating > Estimate Summary.

  2. At the top of the screen, in the tool bar, click the Project ellipsis and select the required project.

  3. If required, click Refresh icon to update the screen.

  4. Click the ESTIMATE SUMMARY tab.

  5. Click the Total Cost hyperlink of the required project object. The estimate details appear in the bottom panel.

  6. Click the SB Estimate Item tab to view the BOQ item summary of the selected project object.

    The line item in the SB Estimate Item tab displays the cost generated after mapping BOQ items with unit rates.