Establish Manual Details - EcoSys - 3.02 - Help - Hexagon PPM

EcoSys Projects Help (3.02)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
3.02

This procedure allows you to update the Cost ETC, Hours ETC, and Quantity ETC for line items of the cost control objects with Manual Details forecast method. The New EAC Details Manual panel provides access to update these details. This panel is not accessible for cost control objects with any other forecast method.

The line items displayed represent a summary of individual line items with the same Cost Account, Resource, and UOM. Several columns such as Actuals, Current ETC, and Current EAC are available to help you establish the new line item ETC.

Line Item ETC values must be established for each project period. Values from the previous project period are not retained.

  1. Navigate to Forecasts > Forecast.

  2. Click the Forecast tab.

  3. Click the New EAC hyperlink for the cost control objects with Manual Details forecast method. The New EAC Details Manual panel appears.

  4. Type the estimated quantity of resources in Manual ETC Quantity column.

  5. Type the estimated number of hours in Manual ETC Hours column.

  6. Type the estimated amount of cost in Manual ETC Cost column.

  7. Click SAVE.

  8. Click REFRESH in the screen above to review the revised New EAC value of the cost control object and understand its impact on the entire project.