View Baseline Comparison of Project Schedule Cost Objects - EcoSys - 3.02 - Help - Hexagon PPM

EcoSys Projects Help (3.02)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
3.02

This process allows you to view mainly the difference in quantities (delta quantity), hours (delta hours), and cost (delta cost) for the cost object which is rescheduled. Also, few other attributes that you can view are quantity, hours, cost, baseline quantity, baseline hours and baseline cost.

  1. Click the Baseline tab.

  2. In the Project Scheduler Set and View Baseline panel, select the cost object row for which you want to view the baseline comparison.

  3. Click the Baseline Compare tab.

    You can customize the view of the Baseline Compare spreadsheet from the view settings.