This procedure allows you to establish the dates method for Smart Build and non Smart Build projects in the Original Budget Time-Phasing panel.

  1. Click the Time-Phasing tab.

  2. Click the Dates Method ellipsis and select the required dates method. The available dates methods are displayed:

    • External Dates

    • Manual

    • Project Schedule

    • Schedule Activity (Min/Max)

    • Smart Build Schedule Dates

      If the dates are available in the ITG_SB ProgressAndDatesAPI API, the Smart Build Start Date and Smart Build End Date auto-populate.

  3. Click the Save icon.

    • When you select a Time-Phasing method, it is mandatory to select a Dates Method for that particular line item.

    • If you select Manual Dates Method, the time phase Start Date and End Date are applied for time phasing. If you select Smart Build Scheduled Dates Dates Method, the Smart Build Start Date and Smart Build End Date are applied for time phasing.