This procedure allows you to update the object actual start and end dates.

  1. Navigate to Progress > Actuals.

  2. In the Project Navigation Register panel, do the following:

    1. (Optional) In the green parameter bar, click the Project Controller ellipsis to select the project controller.

      All the projects that are controlled by the selected project controller are displayed.

    2. (Optional) In the green parameter bar, click the Project Manager ellipsis to select the project manager of the project.

    3. (Optional) In the green parameter bar, click the Portfolio ellipsis to select the portfolio to which the project belongs to.

    4. Select the required project row to view and edit its project details.

      The project details are displayed on the right-hand side.

      (Or)

      On the right-hand side, at the top of the screen, in the green parameter bar, click the Project ellipsis to select the required project.

  3. If required, click REFRESH to update the screen.

  4. Click the Actuals tab.

  5. Select the Actual Start Date.

  6. Select the Actual End Date.

  7. Click the Save icon.

    You can customize the view of the Actual Summary panel from the view settings.