Generate Project Budget Log Report - EcoSys - 2.04 - Help - Hexagon PPM

EcoSys Projects Help (2.04)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
2.04

To view the Project Budget Summary Log report, perform any of the following actions.

  • View the report in the Original Budget screen:

    1. Navigate to Budgets > Original Budget.

    2. Click the Reports tab.

    3. Click the Project Budget Log hyperlink. A dialog box appears with a title Project Budget Log.

    4. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    5. Click the Run button. The preview of the report appears.

  • View the report in the Current Budget screen:

    1. Navigate to Budgets > Current Budget.

    2. Click the Reports tab.

    3. Click the Project Budget Log hyperlink. A dialog box appears with a title Project Budget Log.

    4. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    5. Click the Run button. The preview of the report appears.

  • View the report from the Reports menu:

    1. Navigate to Reports > Budgets > Project Budget Log.

    2. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    3. Click the Run button. The preview of the report appears.