This procedure allows you to build a project schedule by adding durations to tasks and linking the tasks through different kinds of dependencies. The duration and dependencies, as well as the calendar and constraints, are used to auto-calculate task start and end dates and display the schedule’s gantt chart.

  • The tasks on the longest path appear in red. This path is called as Critical Path. The remaining available tasks which are not on the critical path appear in green.

  • If you make a change which cannot be applied, either because the logic is incorrect or the calendar doesn´t allow it, all the bars on the gantt chart will turn yellow and a popup will appear at the bottom right of the screen with information regarding the problem.

  • Clicking the Undo button to causes the recent change to be undone.