A defined set of time-phase methods can be used to establish the Curve, Start Date, and End Date. Once established, these attributes will be utilized when time-phasing the estimate project. The following time-phasing methods can be assigned:

  • Back Loaded: Line items spread in a back-loaded curve.

  • Front Loaded: Line items spread in a front-loaded curve.

  • Linear: Line items spread linearly.

  • Bell: Line items spread in a bell curve.

  1. Navigate to Estimating > Estimate Summary.

  2. At the top of the screen, in the green parameter bar, click the Project ellipsis to view all the estimate details.

  3. Click Refresh for screen update.