The Export Forecasts screen enables you to run an export of forecast information to P6. Considerations for exporting Forecasts are listed below.
-
Data mappings and application settings must first be configured correctly to allow the export to take place.
-
Forecasts for a designated time period are exported.
-
Forecasts for a designated version in EcoSys are exported.
-
Forecasts can be exported using any of the following duration formats: Hour, Month, Week, Quarter, Year.
-
Forecasts can be exported in any currency, provided the currency exists in EcoSys.
-
This functionality allows the export of EcoSys working forecast transactions from Cost Objects into P6. The transactions are exported as resource assignments of a WBS Summary activity, under each project or WBS mapped to cost objects in EcoSys.