Import Resources - EcoSys - Help - Hexagon PPM

EcoSys Primavera P6 Adapter Help

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Version
8.6

Considerations for importing Resources are listed below.

  • You can map P6 resources to existing EcoSys resources, or new resources can be created on import.

  • You can import P6 resource codes as part of this process. In EcoSys, resource codes are created as Resource Categories.

  • You can apply a filter on import using any of the native fields on P6 resources, such as resource type or attributes.

  • When importing P6 Resource custom fields, you must specify custom fields under Import Custom Fields for Minor Period. Click the ellipsis, and then select the minor period. You must first create and specific resource type custom fields in EcoSys in order to import them into this area.