When a project health is published for a selected period, you will not be able to update the project health or KPIs for the same period. To update the project health or KPIs for the already published period, you will have to unpublish it. Once the project health is unpublished, it can be updated and republished. This procedure clears the updated project status information for the selected period.

  1. Click the Actions list and select Unpublish Project Health.

    The Unpublish Project Health dialog box appears.

  2. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    The Project displayed in the green parameter bar at the top of the screen is the only project available for the selection in the Unpublish Project Health dialog box.

  3. Click the Project Period ellipsis to select the required project. By default, the last selected period appears.

  4. (Optional) Type a Comment.

  5. Click the Run button. The Unpublish Project Health confirmation dialog box appears.

  6. Click the OK button. The updated project heath staging and key performance indicators for the selected period is cleared from the Project Status Dashboard screen.

    To view the updated project status, click the Actions list and select Project Dashboard. The Project Dashboard screen appears in a new tab.

  7. Refresh the screen at the browser level to select the period associated with the now unpublished health data.