This procedure allows you to update the project health status and description. The project health status appears with a specific background color as per the RAG (Red, Amber, Green) system that is also used in traffic lights.
The available project statuses are listed below:
-
1 Not Tracking (Red) - the project is not on track to deliver per agreements (schedule, budget, etc.) This indicates that a plan should be developed to bring the project to Tracking status.
-
2 At Risk (Amber) - the project is at risk to deliver per agreements.
-
3 Tracking (Green) – the project is on track to deliver per agreements.
Follow the procedure below to update project health in the Project Health Staging panel:
-
Navigate to Project > Project Reporting Management.
-
Click the New button. This should be done only if the project status has not been copied from the previous period.
-
Click the Project Health Status ellipsis and select the required status. The available project health statuses are listed below:
-
1 Not Tracking
-
2 At Risk
-
3 Tracking
-
-
Type the required Project Health Description.
-
Click SAVE.