This procedure allows you to analyze the health of the project by viewing project KPIs, project metrics, and the project budget status.

  1. Navigate to Project > Project Reporting Management.

  2. At the top of the screen, in the green parameter bar, click the Project and Project Period ellipsis to select the required project and period.

  3. Click Refresh for screen update.

    To view the Project Metrics information, follow the procedure below:

    1. Click the Key Performance Indicators tab to view the KPIs calculated in the Performance Measurement screen.

    2. Click the Project CPI tab to view the CPI value of the project.

    3. Click the Forecast Performance Factors tab to view the updated forecast performance factors.

    4. Click the Project Trends tab. The project health published for the previous months appears in the bar chart.

    5. Click the Percent Complete tab. The % Complete value of project appears

  4. To view the cost information for the project structure, view the Project Budget Status panel.

    • These project cost details include percentage complete, SPI (Cost), original budget, approved changes, current budget, commitments, actuals, forecast changes, earned value, current forecast, and prior forecast.

    • You can customize the view of the Project Budget Status panel from the view settings.