This procedure allows you to re-open a closed risk. Once the risk is reopened, a log entry appears and the status of the risk changes to Identified. This procedure also deletes all the closure details in the Portfolio Risk Details panel.

  1. Navigate to Portfolios > Risks.

  2. Click the Actions list and select Re-Open Portfolio Risk.

  3. Click the Portfolio ellipsis to select the portfolio. By default, the last selected portfolio appears.

    The Portfolio displayed in the green parameter bar at the top of the screen is the only portfolio available for the selection in the Re-Open Portfolio Risk dialog box.

  4. Click the Risk ellipsis icon to select the portfolio. By default, the last selected risk appears.

  5. (Optional) Type a Comment.

  6. Click RUN and then OK. In the Risk Register panel, the status of the selected risk changes to Identified.

    • To view the log entry, click the Log tab.

    • To view the updated risk status, click the Risk Register tab.

    • In the Portfolio Risk Details panel, click the Close Out tab to view the risk closure details. The values in the Closure Commentary, Closed By, and Close Date are cleared.