The Activity Relationship Import is an optional job that creates or updates P6 Activities Relationships to EcoSys Relationships. This import works in conjunction with the P6 Activity to Task Ext Sched Import job. These relationships can be viewed in the EcoSys Scheduling module.
If it is not desired to view P6 Relationships in EcoSys then this import can be skipped.
-
Connect Job: P6 Activity Relationship Import
-
EcoSys Action: ITG P6 Activity Relationship Import
-
Dependencies: P6 Project and WBS Import, P6 Activity to Task Ext Sched Import
Field Mappings
The default behavior of the Activity import is to import the following P6 Activity fields. If desired, any available P6 Activity field could be imported by modifying the Connect Job.
EcoSys Field |
EcoSys Subject Area |
P6 Field |
---|---|---|
TaskSchedulerRelationInternalID |
Task Scheduler Relation |
N/A |
Relation |
Task Scheduler Relation |
Type |
Units |
Task Scheduler Relation |
Set to the Connect Setting "Scheduler.Units" |
Lag |
Task Scheduler Relation |
Lag |
SourceTaskExternalKey |
Task Scheduler Relation |
Predecessor Activity Object Id |
TargetTaskExternalKey |
Task Scheduler Relation |
Successor Activity Object Id |