This procedure allows you to setup potential selections and their corresponding weights for the prioritization factors.

The prioritization score selections should be stand alone and should not have children.

  1. Click the Insert Row icon to add a new prioritization score selection.

  2. Type a required unique ID for the potential level of each prioritization factor.

  3. Type a required unique Name for the potential level of each prioritization factor.

  4. Type the required Weight corresponding to each potential selection of the prioritization factor.

    The sum of the weights of all a prioritization score’s selections must be equal to 100. If not, a project’s prioritization score will not be calculated correctly.

  5. (Optional) Type the Description for the corresponding potential selection of the prioritization factor.

  6. Click the required Parent ellipsis to select the required prioritization factor. The Parent must the value where the ID is Weight.

  7. Click the Save button.

    Click the Delete Row(s) icon to delete the potential selection.