The Dates form is used to view the Budget dates, as well as the user ID and date/time associated with the last update of the Contract Line Item. This form is also used to view high-level project dates and user information.

  1. Navigate to Contracts > Contract Lines.

  2. At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required project.

  3. If required, click REFRESH to update the screen.

  4. Click the Contract Lines Register tab.

  5. Select the Line ID hyperlink. The Contract Line Details panel appears.

  6. Click the Dates tab to view the below data:

    • Original Budget Start Date

    • Original Budget End Date

    • Current Budget Start Date

    • Current Budget End Date

    • Create User

    • Last Update User

    • Create Date

    • Last Update Date