This process allows you to view, add, and update calendars for Resource Management and Scheduling.

  1. Click the Calendars tab.

  2. Click the Insert Row icon to add a new calendar.

  3. Type in the Calendar ID and Calendar Name.

  4. Click the Update hyperlink and select the Time zone for the calendar.

  5. Type in the Start Hour, Start Minute, and Duration (Hours).

  6. Select the Working Day check boxes for the required calendar.

    • To remove unused calendar, click the Delete Row(s) icon. The calendars that are already in use cannot be deleted.

    • You can customize the view of the Schedule Calendars panel from the view settings.

Schedule Calendar Overrides

This process allows you to override an existing calendar with working and non-working dates.

  1. In the Schedule Calendars panel, select the calendar row for which you want to override.

  2. In the Schedule Calendar Overrides panel, click the Insert Row icon to add a new row for the calendar override date.

  3. Select the Override Date.

  4. If the override is to work on the override date, select the Is Working check box.

  5. Type in the Start Hour, Start Minute, and Duration (Hours).

    • If the Duration (Hours) field is empty, the field is highlighted in red color.

    • To remove a schedule calendar override, click the Delete Row(s) icon to delete the row.