This procedure allows the resource manager to view the approved resource utilization for the selected project.
-
Click the APPROVAL PORTAL tab.
-
Click the Approved Utilization hyperlink to view the approved utilization of resource(s) for the selected project.
-
(Optional) In the Approved Utilization panel, click the Resource ellipsis and select the particular resource to view the resource utilization.
-
Click the Discipline hyperlink.
-
In the Resource Availability Approved panel, click the Check Availability ellipsis, and select Yes.
-
Click SAVE. The Resource Availability details appear in the Resource Availability graph.