This procedure allows you to view the resource capacity plan by project and resource availability by discipline between selected weeks in a graphical format and resource details.

  1. Navigate to Resource Management > Supply/Demand.

  2. Click the Year ellipsis and select the year for which you want to view Resource Capacity Plan.

  3. Click the Analysis tab.

  4. In the Capacity Plan panel, click the Start Week and End Week ellipsis and select the weeks.

  5. (Optional) Click the Resource ellipsis and select the required resource.

  6. Click the Resource ID hyperlink. The following panels get updated:

    • Utilization Plan by Project - The selected resource utilization in his/her assigned projects are displayed.

    • Resource Availability by Discipline - The resource availability by discipline is shown in a graphical format based on month and week.

    • Resource Details - The Key Information, Skills and Location details of resource are displayed.