This procedure allows you to update the project schedule baselines for the enterprise.

  1. Navigate to Admin > Projects Admin > Project Schedule Admin.

  2. Click the Baselines tab.

  3. Click the Insert Row icon.

  4. Type in the ID and Name of the baseline.

  5. Type the description for the baseline in the Description field.

  6. Click SAVE.

    Click the Delete Row(s) icon to delete the selected row.