This procedure allows you to create overrides to the selected enterprise calendar.

  1. Navigate to Admin > Projects Admin > Project Schedule Admin.

  2. In the Schedule Calendar Overrides panel, click the Insert Row icon to add a new row.

  3. Select the Override Date.

  4. Select the Is Working check box if this is a working day.

  5. Type in the Start Hour and Start Minute.

  6. Type in the Duration.

  7. Click SAVE.