This procedure allows the resource manager to view the approved resource utilization for the selected project.

  1. Click the APPROVAL PORTAL tab.

  2. Click the Approved Utilization hyperlink to view the approved utilization of resource(s) for the selected project.

  3. (Optional) In the Approved Utilization panel, click the Resource ellipsis and select the particular resource to view the resource utilization.

  4. Click the Discipline hyperlink.

  5. In the Resource Availability Approved panel, click the Check Availability ellipsis, and select Yes.

  6. Click SAVE. The Resource Availability details appear in the Resource Availability graph.