This procedure allows you to view the resource availability between selected weeks in a graphical format based on month and week.

  1. Click the Analysis tab.

  2. In the Availability by Resource panel, click the Start Week and End Week ellipsis and select the weeks.

  3. Click the Resource ellipsis and select the required resource.

    The resource availability is displayed in a graphical format based on month and week.