This procedure allows the project manager to backout all the resource request for a project.

  1. Click the Actions list and select Submit Project Requests.

  2. Click the Project ellipsis and select the project for which you want to backout resources.

  3. Click RUN and then OK.

    All the Submitted Utilization requests for the selected project are moved back to Staging state.