Tasks - EcoSys - 2.04 - Administration & Configuration - Hexagon PPM

EcoSys Core and Projects Administration (2.04)

Language
English
Product
EcoSys
Search by Category
Administration & Configuration
EcoSys Standard Version
2.04

In the Tasks screen, you can add, update, or delete project-related tasks. This screen should be only used by EcoSys configurators.

To view or update project tasks, navigate to Admin > Projects Admin > Tasks.

  • To view or update the project budgets, click the Budgets tab.

  • To view or update the project changes, click the Changes tab.

  • To view or update the project commitments, click the Commitments tab.

  • To view or update the project deliverables, click the Deliverables tab.

  • To view or update the project risks, click the Risks tab.

  • To view or update the project issues, click the Issues tab.

You can customize the view of the project Budgets, Changes, Commitments, Deliverables, Risks, Issues, Estimates spreadsheet from the view settings.