Systematic (non-manual) time-phasing is performed using the Time-Phase Unapproved Change action. This action will spread the costs, quantities and hours based upon the change header Start Date, End Date, and Curve displayed in the Contract Change Details panel.

  1. Navigate to Changes > Contract Changes.

  2. Click the Actions list and select Time-Phase Unapproved Change.

  3. Click the Contract ellipsis to select the required contract.

  4. Click the Contract Change ellipsis to select the required contract change.

  5. Click RUN.