TheTime-Phasing tab displays Quantity, Hours, and Cost across a range of time periods for all Contract Line Items. If the "Manual" curve type has been selected for a specific Contract Line Item, period values may be directly edited.

  1. Navigate to Budgets > Contract Budget.

  2. At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required project.

  3. If required, click REFRESH to update the screen.

  4. Click the Contract Budget Register tab.

    You can update the changes only in Open status.

  5. Click the Line ID hyperlink. The Contract Budget Manual panel appears.

  6. Click the Time-Phasing tab.

  7. Select a Start Period and an End Period to display a range of Quantity, Hours and Cost columns beginning with the Start Period and ending with the End Period.

  8. Set up the budget time-phasing details as indicated below:

    1. Select a Line ID with "Manual" Curve.

    2. (Optional) Spread Quantity across periods.

    3. (Optional) Spread Hours across periods.

    4. (Optional) Spread Cost across periods.

  9. Click SAVE.

    You can customize the view of the Contract Budget Manual panel from the view settings.